South East Aylesbury Link Road (SEALR)

 

Scheme overview

Where:

South East Aylesbury – Stoke Mandeville

When:

Due for completion by the end of 2021.

Summary:

This project will create a link road between the A413 Wendover Road and the B4443 Lower Road.

Status:

Refinements to the scheme following the public consultation have been completed. The planning application is close to submission. Detailed design and Early Contractor Involvement work have begun.

Next Steps:

Planning application consultation through the Planning Authority. View the planning application

Contact:

hitmailbox@buckscc.gov.uk | 01296 395 000


About the project

The South East Aylesbury Link Road will connect the B4443 Lower Road with the A413 Wendover Road. It is required to ease congestion after HS2 Ltd. realigns the A4010 through the construction of the Stoke Mandeville Relief Road.

The road will link with the realigned A4010 ‘Stoke Mandeville Relief Road’. This is being delivered as part of the HS2 project. This forms part of the Aylesbury Transport Strategy.

 

What's changing?

The new dual carriageway will consist of:

  • A new roundabout to access the SEALR at the junction of the B4443 and the A4010 realignment to the south.
  • A new roundabout on the A413 Wendover Road.
  • An overbridge crossing the Aylesbury to Marylebone line (funded by HS2).

The Aylesbury Link Roads proposal has been a long held ambition for Buckinghamshire County Council. The growth and development of Aylesbury has made these proposals a necessity.

View the overall Transport Plan for Aylesbury.

 

What's happened so far?

The following items have already been completed in the project:

  • Consultants have been appointed to take forward the planning application and the business case.
  • Funding has been confirmed through HS2 Ltd. and the Local Growth Fund (via the Buckinghamshire Local Economic Partnership).
  • The first consultation took place on the 1 November 2017.
  • Refinements to the project following the consultation have been completed.
  • The updated project designs were presented on the 17 July 2018.
  • Surveying of land to inform design has begun and is underway.
  • Transport modelling to further inform design has begun and is underway.
  • Contractors have been appointed for Early Contractor Involvement.
  • The planning application was submitted on 20 March 2020.

Our consultation section below has more details on this.

 

What's next?

  • Planning Application Statutory Consultation to be arranged via the Planning Authority
  • Discussions with landowners will continue.

 

Plans of the scheme

The proposed layout of the South East Aylesbury Link Road is shown in our updated preliminary designs.

View the exhibition board plans from the public event on the 17 July 2018.

Below is a video simulation of how the South East Aylesbury Link Road may look.

 

Consultation

The first public consultation on the SEALR took place from the 1 November to the 8 December 2017. View the consultation summary document for an overview of the responses received.

Changes have been made to the scheme in order to address some of the comments raised during the first consultation period. The new updated scheme was presented at an exhibition event on the 17 July 2018.

 

Planning application

The planning application for the scheme was submitted on the 20 March 2020.

View the planning application

A statutory consultation will be completed for this scheme by the planning authority this is due to end on the 10 June 2020.

 

Bulletins

View our previous bulletins for the South East Aylesbury Link Road

 

Print entire guide

Last updated: 14 May 2020

Was this page helpful?

Very poor
Poor
Neither good nor poor
Good
Very good