A418 Oxford Road corridor improvements

View our bulletins to keep up to date with the latest changes. To receive email updates when new bulletins are added, subscribe to the mailing list.

View bulletins

The project is being delivered in a number of stages to reduce the traffic impact and delays on the A418.

The first stage of the works for a shared footway/ cycleway at Pearson Close, Pearl Way to Thame Road South, Pebble Way was completed 3 December 2019.

The second stage of the main works started 9 December 2019 at the Fowler Road junction until 27 March 2020 and includes:

  • new shared use footway/cycleway between Fowler Road and Oxford Road
  • widening of Fowler Road to provide an extended left turn lane into Oxford Road

These works are substantially complete. The carriageway resurfacing work on Fowler Road was completed on 20 March 2020 and the new road markings and slot cutting were finished on 27 March 2020.

The third stage of works to upgrade three pedestrian crossings along the A418 Oxford Road corridor started on the 27 January 2020 and was completed on 20 March 2020.

The pedestrian crossing upgrades will make it possible for them to better adapt to traffic flows and pedestrian demand and they will be linked to each other and the Fowler Road/ Churchill Avenue junction to allow control of flows on the A418 Oxford Road corridor.

The central island outside Sir Henry Floyd Grammar School was extended to prevent vehicles exiting right out of the school and causing delays. This work was completed on 12 June 2020.

On the 29 June 2020, work started on the fourth stage of the project, for a period of 15 weeks. The work is progressing well and is expected to be completed on 2 October 2020.

From Wednesday 22 July to 4 September 2020, the works for the road widening on Churchill Avenue will require the Southcourt-bound lane to be closed over the summer holidays. The works will be undertaken during peak times between 8am and 5pm to allow a section of the grass verge to be used to widen the road.

Diversion route 1
Diversion route 2

 

Works planned from week commencing 20 July 2020

The following works are being undertaken between 20 July and 2 October 2020:

Description of works Date Proposed traffic management Duration

New ducting works at Oxford Road/ Churchill Avenue junction 

20 July to 19 Aug 2020

Temporary signals replicating the existing permanent signals. Works to be undertaken between 8am and 5pm

5 weeks

Churchill Avenue widening works (Phase 2)

20 to 22 July 2020

Footway closure and 'Stop and Go' with lane closures between 8am and 5pm

3 days

Churchill Avenue widening works (Phase 3)

22 July to 4 Sep 2020

Eastbound road closures in place 24 hours a day. This will result in no left turns from A418 into Churchill Avenue during the summer holidays

7 weeks

Churchill Avenue widening works (Phase 4)

7 to 24 Sep 2020

Footway closure and 'Stop and Go' with lane closures between 8am and 5pm

3 weeks

Resurfacing and line marking works at Churchill Avenue

25 Sep to 2 Oct 2020

Road closed between 7pm and 6am

1 week

Overview plan of the works to be undertaken at the Churchill Avenue junction

Overview plan of the works to be undertaken at the Churchill Avenue junction.

 

Temporary Traffic Management

  • Normal day working hours are between 8am and 5pm (Monday – Friday)
  • Normal night working hours are between 7pm and 6am (Monday – Friday)
  • Information signs have been erected to highlight the planned works, dates and duration of works
  • We will continue to maintain normal access and emergency access to properties during the works

We recognise that there is likely to be traffic disruption during the works and we will continue to monitor conditions closely and respond accordingly.

 

Overview

To address congestion and support economic growth a number of improvements along the A418, Oxford Road were identified, and formed part of a successful National Productivity Investment Funding bid to Government in 2017. The funding was secured against a suite of measures along the A418 corridor which aim to ease urban congestion, improve air quality, enable the future delivery of development sites and build resilience into the transport network. 

Following the public consultation that was carried out in the summer a Cabinet Member decision was taken at the beginning of November to approve the implementation of a combination of local junction improvements, sustainable transport improvements and the introduction of new technology to allow smarter management of the corridor.

Work has been underway since 2017 to introduce a number of the corridor improvements to realise the benefits as soon as possible. This has comprised installation and preparatory works for a number of new corridor technologies including:

  1. Installation of chamber, ducting, and loop boxes; carriageway duct crossing across A418 (Mill Lane – pedestrian crossing and west side of Friarage Road).
  2. Installation of chamber, ducting, and carriageway loop boxes on the south side footway of A418 Oxford Rd – North East of A41 Gatehouse Road.

To help improve traffic flow and ease congestion, a number of junction upgrades and cycleway improvements are also proposed along the A418 Oxford Road Corridor, comprising:

  • A418/ Fowler Road/ Churchill Avenue crossroads – Carriageway widening, improved signal timings and construction of a new shared use footway and cycleway.
  • Pearson Close/ Thame Road South cycleway connectivity – Construction of a new shared use footway and cycleway to link into the existing Gemstones routes, Improvements to uncontrolled crossing facilities, including new signs and tactile paving.
  • Upgraded and linked traffic signal equipment at junctions and crossings, allowing signal timings to better adapt to traffic flows and pedestrian demand.
  • Upgraded permanent Variable Message Signs (VMS) to provide information to road users, such as network traffic conditions, road closures and parking space availability.
  • Closed Circuit Television (CCTV) to monitor traffic flows and help manage incidents.
  • Real Time Passenger Information (RTPI) units at bus stops, providing up-to-date transport information.
  • An upgraded bus shelter outside Sir Henry Floyd Grammar School and Aylesbury College.

 

About the project

The A418 Oxford Road currently supports a high volume of daily traffic. The traffic causes congestion, particularly during peak times. This congestion is set to worsen as vehicle numbers increase in the future.

This project seeks to deliver a coordinated package of improvements to the corridor which will deliver the main objectives of the project to:

  • improve journey time reliability
  • ease congestion
  • encourage increased sustainable travel
  • improve air quality

View the A418 Oxford Road corridor improvement plan.

Map of the A418 plan

 

Funding

Buckinghamshire County Council submitted a funding bid to the Department for Transport’s (DfT) National Productivity Investment Fund (NPIF). The funding is to help tackle existing congestion problems, unlock housing, and enable economic growth.

The total budget for the scheme is £2.69M comprising:

  • successful NPIF bid of £2.191M
  • developer funding of £500,000

 

Project improvements

New technology

The installation of new technology will allow better management of traffic flows. It will also assist in the management of traffic during incidents on the network from the Council’s central control centre.

The technology improvements will include:

  • Upgrading traffic signal equipment at junctions and crossings, allowing signal timings to better adapt to traffic flows and pedestrian demand.
  • Linking traffic signals along the Oxford Road to allow control of flows on the corridor
  • Traffic detectors installed in the road to sense traffic flows and queues, allowing traffic signals to adapt to the traffic conditions.
  • CCTV (closed circuit television) improving safety, monitoring traffic flows and providing information to help manage incidents.
  • Variable message signs (VMS) providing information to road users, such as queue times, road closures and parking space availability.

Junctions and cycleways

Pearson Close/ Thame Road South cycleway connectivity

  • Construction of a new shared use footway and cycleway between the Pearl Way and Pebble Way existing Gemstone routes at the A418/ Ellen Road roundabout. This will include improvements to uncontrolled crossing facilities, new signs and tactile paving, and refreshed cycleway and footway surfaces.

A418/ Fowler Road/ Churchill Avenue crossroads

  • Capacity improvements through the widening of two arms of the junction and improved signal timings.
  • Extension to the left-hand filter lane from Fowler Road into Oxford Road (eastbound) through carriageway widening from 14m to 90m. 
  • Extension of the two lane approach to the junction from Churchill Avenue from 15m to 120m through carriageway widening. 
  • Construction of a shared use footway and cycleway extension to the existing Pearl Way route to create a more direct path from Fowler Road to Oxford Road.

Sir Henry Floyd Grammar School and Aylesbury College

  • Introduction of a traffic island to prevent coaches and buses turning right out of the coach park onto the A418.
  • Installation of part-time traffic signals on the exit of  the School/ College site to help reduce the queuing on Oxford Road caused by right turning traffic exiting from the school by helping to create gaps when vehicles are held at the signal.

A418/A41 roundabout

  • Changing the existing toucan crossing on the A41 Gatehouse Road into a staggered crossing with an island so that the traffic lights for both lanes work on separate signals and reduce the time that vehicles need to wait. This requires the relocation of seven residential parking bays on A41 Gatehouse Road.
  • An unused section of bus lane on the approach to the roundabout will be removed, as well as the removal of a bus stop to improve access for buses into the roundabout.
  • New section of shared use footway and cycleway to link the Pearl Way and Ruby Way routes.
  • This work will be complemented by technology improvement to link and co-ordinate the traffic signals at the roundabout to help to create gaps and improve the flow of traffic. The signals at the Mill Way and Territorial Army (TA) Centre pedestrian crossings will be upgraded and linked.

 

Public transport

The A418 Oxford Road is an existing Public Priority Transport Corridor with a dedicated inbound bus lane. By easing congestion, the project will reduce delays and speed up bus journey times.

There will be improvements to bus stops along the route, including:

  • a new bus shelter
  • installation of real-time passenger information units providing up to date scheduling information

 

Consultation

A consultation period was open from Wednesday 10 July 2019 to Friday 9 August 2019. Plans for the junction and cycleway proposals were shared with the public. This includes an overview of the coordinated package of improvements along the road.

A public exhibition event was held on Thursday 18 July, 2pm to 8pm at the Aylesbury Campus of the Bucks College Group. Following this consultation, responses were summarised in a report to the Cabinet Member for a decision to proceed with the project. A Cabinet Member decision was taken on 4 November 2019 to approve the implementation of a combination of:

  • local junction improvements
  • sustainable transport improvements
  • introduction of new technology to allow smarter management of the corridor

 

Supporting documents

A418 Consultation Brochure
A418/A41 roundabout
A418/Fowler Road/Churchill Avenue crossroads
Journey time improvements
New corridor technology
Scheme overview
Welcome banner
Project timeline and benefits

 

Department for Transport logo

 

Was this page helpful?

Very poor
Poor
Neither good nor poor
Good
Very good