The A4010 and A4129 roads in West Wycombe and Princes Risborough have been identified by HS2 Ltd for use as construction routes whilst the new railway is built. 

Construction is expected to start in August 2019.

 

About the project

We are working with the A4010 and A4129 petitioners group to deliver important safety measures between Princes Risborough and High Wycombe. The project has been developed in partnership with the Petitioner Group, consisting of members from the following councils:

  • Wycombe District Council
  • Princes Risborough Town Council
  • Bradenham Parish Council
  • West Wycombe Parish Council

 

Consultation

The safety improvement works consultation ran from 24 May 2019 to 14 June 2019.

Following the consultation, the plans and construction have been approved by the Deputy Leader & Cabinet Member for Transportation. View the key decision report.

 

Construction

The list of schemes will be delivered within the available HS2 Ltd funding (£541k).

These sites have been through internal stakeholder review, public consultation, and construction works tender exercise. Following approval, construction is expected to begin from the end of August 2019 with roadworks lasting approximately 3 months.

Site 2 - St Teresa’s School Frontage
Site 3 - Monks Risborough School Frontage 
Site 4 - Bradenham Bends improvements
Site 5 - New Wycombe Road Zebra Crossing
Site 6 - Longwick Road Entry Feature with a Variable Message Sign
Site 7a - Longwick Road Zebra Crossing Belisha beacon upgrade
Site 7b - Aylesbury Road Pedestrian Crossing updated signage
Site 9 - Monks Risborough Entry Feature with a Variable Message Sign
Site 10 - Princes Risborough Entry Feature with a Variable Message Sign
Site 13 - Bradenham Road Pedestrian Refuge
Site 14 - Bradenham Road Bus Shelter with revised hard standing construction
Site 15 - New Aylesbury Road Zebra Crossing
Site 16 - New Road pedestrian refuge and signage

View the overview of approved plans.

The schemes proposed at sites 1a, 1b, 8, 11, 12, 17a, 17b & 18 will no longer be delivered as part of this project. These sites will be placed on hold unless additional funding sources are identified.

 

Contact

For any questions or queries:

Highways Infrastructure Project Team
Email: hitmailbox@buckscc.gov.uk
Telephone: 01296 382 416

 

Was this page helpful?

Very poor
Poor
Neither good nor poor
Good
Very good