3. Berryfields phase 3

Phase 3 will involve:

  • Completion of the Northern Loop Road
  • Completion of the Northern Link Road
  • Implementation of the first part of the Western Link Road up to the first roundabout(365m)
  • Implementation of the remainder of the Eastern Loop Road

Phase 3 will be on site from September 2012 - April 2013. The extent of the works is shown on the plan attached below.

Section 1 (Red) is expected to be completed by the end of 2012/early 2013. The section of Berryfields Lane currently under temporary traffic signal control should be open to 2 way traffic by the end of November 2012.

Section 3 (Blue) is expected to be completed in April 2013 but it is unlikely to be able to be used by the public due to construction of the development continuing adjacent to the new roads.

Section 2 (Green) timescales for this to be announced.