Coronavirus support and information
Local information on coronavirus, including service changes, business support, how to get help and vaccinations.Temporary Traffic Regulation Orders
Anyone may apply for a temporary Traffic Regulation Order (TRO) under the Road Traffic Regulation Act 1984, Section 14, affecting any public highway (whether road, footpath, cycleway, bridleway, etc) in Buckinghamshire, where a closure or restriction is in order to effect works on, within or adjoining the highway, or is necessary in the interests of public safety because of such works or other circumstances.
Three months notice is required for closure (including special events). The maximum temporary closure is six months, but the applicant can reapply to extend this, giving two months notice. From 1 April 2019, the charge for each closure is £1,820.
If the requisite period of notice is not received, the authority may require the works or event in question to be deferred. It is important that the closure period is adequate to cater for any possible contingency. An extension cannot be guaranteed but would incur further costs. The maximum period that the highway or right of way is expected to be closed must be indicated, and will be advertised within any publicity given by the authority.
An Order or Notice temporarily prohibiting through vehicular traffic from using a highway has the effect of closing the highway in question, but normally protects pedestrian use and rights of access to properties along the affected highway. Applicants will be required to ensure that such access is possible at all times, or, if this is not possible, to ensure that alternative arrangements are made which are satisfactory to all affected parties.
Similar arrangements exist in relation to the closure of footpaths, etc where Orders or Notices prevent pedestrians, cyclists or horse-riders from using a particular route. In the case of requests for an Order affecting a non-vehicular route, it will be assumed that the complete closure of the right of way is sought unless otherwise stated. Applicants should discuss the proposals with a rights of way officer before submitting the application.
HS2 Construction: closures and diversions
Temporary rights of way closures and diversions will take place throughout the construction of HS2.
View HS2 closures and diversions or find out more on the HS2 website.
Contact
For further information please get in touch.
Definitive Map Team
Buckinghamshire Council
Walton Street Offices
Aylesbury
HP20 1UY
Telephone: 01296 395 000
email: row@buckinghamshire.gov.uk
Current routes affected by temporary closure
Road number |
Local community area |
Section works |
Work |
Start |
Finish |
---|---|---|---|---|---|
The Buckinghamshire County Council (Byways Open to All Traffic Nos. 7 and 8, Parish of Princes Risborough) (Prohibition of Driving) Order 201 |
Princes Risborough |
Byways Open to All Traffic Nos. 7 and 8 Princes Risborough |
Annual Prohibition of Driving Order |
1 November to 31 December, 1 January to 30 April inclusive each year |
30 April each year |
The Buckinghamshire County Council (Byway Open to All Traffic No. 92, Parish of Bledlow-cum-Saunderton) (Prohibition of Driving) Order 201 |
Bledow-cum-Saunderton |
Byway Open to All Traffic No. 92 Blewlow-cum_Saunderton |
Annual Prohibition of Driving Order |
1 November to 31 December, 1 January to 30 April inclusive each year |
30 April each year |
Public Footpath No.36 Buckingham |
Buckingham |
From a point approximately 162 metres North West of Gawcott Road, to Footpath junction with the A421. |
Development of 400 dwellings and infrastructure. The outline planning reference is 15/01218/AOP |
1 April 2018 |
30 March 2022 |
Public Footpaths No. 15 & 16 Haddenham |
Haddenham |
Public Footpath No.16 Haddenham From the junction of Stanbridge Road approximately 472 metres Southwest to the junction of Public Footpath No.15 Haddenham.
Public Footpath No.15 Haddenham From the junction of Churchway approximately 566 metres South east to the junction of Aston Road |
Construction Purposes |
12 March 2018 |
19 September 2021 |
Public Bridleway No.71 High Wycombe |
High Wycombe | From the junction of Lily’s Walk South for approximately 103 metres to the junction of Queen Alexandra Road | Approved Development at Lily’s walk | 18 September 2020
|
18 March 2021 |
Public Footpath No.8 and 9 Bierton with Broughton |
Bierton With Broughton | Public Footpath No.8 Bierton with Broughton From the junction of Public Footpath No.13 Bierton with Broughton to a point approximately 760 metres North north east Public Footpath No.9 Bierton with Broughton From the junction of Public Footpath No.13 Bierton with Broughton to a point approximately 530 metres |
To allow for works to proceed in connection with approved development | 2 July 2018 | 2 January 2022 |
Public Footpath No. 10 Stoke Mandeville | Stoke Mandeville | The entire length of Public Footpath No.10 Stoke Mandeville from Old Risborough Road to the junction of Public Footpath No.8 Stoke Mandeville | To allow for safe construction of a Multi-plot Residential Development | 1 June 2019 | 1 August 2021 |
Public Footpath No. 59 | High Wycombe | The entire length of footpath no 59 | To allow for safe construction of a Residential Development | 1 April 2019 | 1 April 2021 |
Public Footpath No.22 and No.23 Dorney | Dorney | Public Footpath No. 23/1 Parish of Dorney from Glebe Close to Old Marsh Lane and Public Footpath No. 22/1 Parish of Dorney in its entirety | The closure is required in the interest of public safety during the demolition and construction of Marsh Lane bridge | 17 June 2019 | 22 July 2021 |
Public Footpath No.8 Bierton with Broughton | Bierton with Broughton | From the junction of Gibb Lane to a point approximately 800 metres South and South East | To enable the development of the land in accordance with planning approval 10/02649/AOP & 15/01767ADP for 892 plots and associated infrastructure | 8 July 2019 | 20 January 2022 |
Public Footpath No.5 Calvert Green and Footpath No.17 Steeple Claydon |
Calvert Green and Steeple Claydon |
Public Footpath No.5 Calvert Green and Public Footpath No.17 Steeple Claydon from Public Bridleway No.18 Steeple Claydon South West to Public Footpath No.4 Calvert Green | In the interest of Public Safety to allow landfill operations on Calvert site to continue | 9 March 2019 | 31 December 2020 |
Public Footpath No 20 and Public Bridleway No. 31 |
Iver |
Public Footpath No.20 from junction with Old Slade Lane for a distance of 180m south west, Public Bridleway No. 31from Old Slade Lane for a distance of 230m south east. | The closure is required in interest of public safety during demolition of Old Slade Lane bridge and construction of new bridge. | 2 October 2020 | 2 March 2021 |
Public Footpath No.18 Longwick-cum-ilmer |
Longwick-Cum-Ilmer |
Longwick-Cum-Ilmer No.18,Which commences at its junction with Owlswick and continues for a distance of approximately 175m in a north-east direction. | Improvement works to Right of Way | 4 December 2020 | 4 May 2021 |
Public Footpath No.50 Stokenchurch |
Stokenchurch |
The whole length of footpath No.50 |
The closure is required in the interests of public safety whilst road widening and infrastructure installation works take place. |
2 October 2020 | 2 March 2021 |
Public Footpath No.11 Wingrave |
Wingrave |
Junction with Twelve Leys and continues to its junction with Nup End Lane |
Development Works | 21 September 2020 | 21 May 2022 |
Public Footpath No.6 Steeple Claydon |
Steeple Claydon |
Public Footpath No.6 Steeple Claydon from outside No.1 Adison Road bearing in a south-westerly direction for a length of 150 metres. |
Development works | 1 March 2020 | 1 March 2022 |
Public Footpath No.37 Penn |
Penn |
Entire length of Public Footpath No.37 Penn |
Tree Works | 2 November 2020 | 2 May 2021 |
Public Bridleway No.36 Quainton |
Quainton |
From a point approximately 660 metres from the junction of Lawn Hill to a point approximately 820 metres from the junction of Lawn Hill. |
Public safety and to allow works on the bridge to be undertaken | 5 October 2020 | 17 June 2021 |
Public Footpath No.4 Soulbury |
Soulbury |
From a point approximately 409 metres east of the junction with Soulbury Road to a point approximately 479 metres east of the junction with Soulbury Road |
Public safety due to the surface being out of repair and damaged. | 25 November 2020 | 23 May 2021 |
Public Footpath No. 9 Amersham |
Amersham |
Whole length of the path, which commences at end of Longwood Lane to its junction with Stanley Hill Avenue. |
Public safety - works to install a new high voltage electrical cable. | 11 January 2021 | 1 March 2021 |
Public Footpath No. 2 Stoke Poges |
Stoke Poges |
From Muddy Lane to the junction with Fir Tree Avenue |
Public Safety due to the approved development. |
22 January 2021 |
22June 2021 |
Public Footpaths Nos. 6 and 7, Chalfont St Peter |
Chalfont St Peter |
Footpaths located within Newlands Park |
Public Safety to facilitate a film production |
1 February 2021 |
31 December 2021 |
Public Footpath Nos. 3, 4 & 6 |
Aston Clinton |
In certain lengths of Public Footpath Nos. 3,4 & 6 in the vicinity of Green End Street |
Construction Works |
3 February 2021 |
3 August 2021 |
Public Footpath No.34 Great Missenden |
Great Missenden |
In that length of Public Footpath No.34 Great Missenden, for a distance of approximately 270 metres in a southerly direction to its junction with Great Missenden No.33 |
Crossover works |
17 February 2021 |
17 August 2021 |
Public Footpath No.4A and No.5 Stokenchurch |
Stokenchurch |
Entire length of Public Footpath No.5. That length of Footpath No.4A which commences at a junction with footpaths No.5 and continues for a distance of approximately 150 metres in a northerly direction That length of Footpath No.5 which commences at a junction with footpaths No.4A and 5 and continues for a distance of approximately 100 metres in a westerly direction |
Development Works |
1 March 2021 |
1 September 2021 |
Public Footpath No.9 Chearsley |
Chearsley |
Length of Public Footpath No.9 Chearsley for approximately 50 metres either side of the level crossing |
Level Crossing Works |
1 March 2021 |
1 September 2021 |
Public Footpath No.17 Stoke Mandeville |
Stoke Mandeville |
Length of Public Footpath No.17 Stoke Mandeville for approximately 50 metres either side of the level crossing |
Level Crossing Works |
1 March 2021 |
1 September 2021 |