HS2 Construction: closures and diversions

Temporary rights of way route closures and diversions will start in January 2018 and last for at least 7 to 8 years.

These will include preparation works such as:

  • environmental mitigation
  • archaeology
  • installation of haul roads
  • utility works (moving gas, water and electricity apparatus)

Construction of the railway line and tunnel through the Chilterns will begin when the preparation works are complete.

Closures and diversions for walkers, cyclists and horse riders around the construction works are below. Maps linked within 'Section Works' show alternative routes and likely length of closure.

All closures are taking place using powers outlined in the High Speed Rail (London – West Midlands) Act 2017. Reports and maps of the construction areas and the route itself can be found on the gov.uk website.

 

Road Number

Local Community Area

Section Works

Work

Start

Finish

Public Footpath No. 44 Chalfont St Peter

Chalfont St Peter

FP44 Closure 

1003m south from Chalfont Lane to junction with Bridleway 2 Denham Parish and Bridleway 43 Chalfont St Peter. The alternative is along Public Bridleway 43 and under the M25 to Denham Lane, then north through Chalfont St Peter, and east along West Hyde Lane, as per enclosed map

Boundary fencing and power supply installation works for HS2 by Fusion subcontractor Amey

1 February 2019

31 January 2020

Public Footpath No. 6 Steeple Claydon

Steeple Claydon Footpath Reference  Plan - Bucks CC
Construction Works for Pipeline. Public Safety
18 April 2018 31 January 2019

Public Footpath No.7 Steeple Claydon

Steeple Claydon Footpath Reference  Plan - Bucks CC

Construction Works for Pipeline.

Public Safety
18 April 2018 31 January 2019

Public Footpath No.8 Steeple Claydon

Steeple Claydon Footpath Reference  Plan - Bucks CC

Construction Works for Pipeline.

Public Safety

18 April 2018  31 January 2019 

Public Footpath No.9 Steeple Claydon

Steeple Claydon Footpath Reference  Plan - Bucks CC

Construction Works for Pipeline.

Public Safety

18 April 2018  31 January 2019 

Public Footpath No.4 Twyford

Twyford Footpath Reference  Plan - Bucks CC

Construction Works for Pipeline.

Public Safety

18 April 2018   31 January 2019 

Public Footpath No.7 Hogshaw

Hogshaw Public Footpath No.7 Hogshaw
From the junction of Claydon Road to the junction of Public Footpath No.7 East Claydon. Approximately 685metres

Overhead Power lines

1 July 2019 31 December 2019

Public Bridleway No.40 Quainton

Quainton From the junction of Claydon Road West north west for approximately 890 metres to the junction of Public Footpath No.38 Quainton

Overhead Power Lines

1 July 2019 31 December 2019

Public Footpath No.38 Quainton

Quainton From a point approximately 760 metres North from Claydon Road to the junction of Public Bridleway No.40 Quainton

Overhead Power Lines

1 July 2019 31 December 2019

Public Footpath No.39 Quainton

Quainton From a point approximately 435 metres North west of Claydon Road to a point 756metres North West

Overhead Power Lines

1 July 2019 31 December 2019

Public Footpath No.35 Quainton

Quainton From a point approximately 776 metres West of Claydon Road to the junction of Public Footpath No.35A Quainton

Overhead Power Lines

1 January 2019 31 November 2019

Public Footpath No.35A Quainton

Quainton From the junction Of Public Footpath No.35 Quainton south for approximately 400 metres to the road junction

Overhead Power lines

1 January 2019 31 November 2019

Public Footpath No.26 Quainton

Quainton From the Road junction just off of North Cottage to a point approximately 910 metre East

Overhead Power Lines

1 April 2019 3 November 2019

Public Footpath No.25A Quainton

Quainton From the junction of the unnamed road approximately west then south west to the junction of Public Footpath No.25 Quainton

Overhead Power Lines

1 May 2019 30 September 2019

Public Footpath No.25 Quainton

Quainton From the junction of the unnamed road to the junction of Public Footpath No.6 Grendon Underwood

Overhead Power Lines

1 May 2019 30 September 2019

Public Footpath No.8 Grendon Underwood

Grendon Underwood From the junction of the unnamed road west north west to the junction of Public Footpath No.6 Grendon Underwood

Overhead Power Lines

1 May 2019 30 September 2019
Public Bridleway No 19 Stone with Bishopstone & Hartwell

 

Stone with Bishopstone & Hartwell Between SP80826-10832 and SP81420-11303

Closure is required for safety reasons to allow for vegetation clearance

2 September 2019 22 November 2019
Public Bridleway No 19 Stone with Bishopstone & Hartwell Stone with Bishopstone & Hartwell Between SP80826-10832 and SP81420-11303

Closure is required for safety reasons to allow for wiring works

3 February 2020 17 July 2020
Public Footpath No.16 Stoke Mandeville Stoke Mandeville Between SP81715-10933 and SP81525-10594

Closure is required for the installation of a National Grid Tower and pylon restringing. The closure will commence when works start and the footpath is fenced off.

2 September 2019 30 September 2020

Public Footpath No.11 Stoke Mandeville

 

No.31 Great and Little Kimble

 

No.29 Stone with Bishopstone and Hartwell

Stoke Mandeville, Great and Little Kimble and Stone with Bishopstone and Hartwell Between SP82592-10791 and SP82154-09618

Closure is required for safety reasons due to the proximity of tower and to allow works of restringing of conductors between towers.

2 September 2019 30 September 2020
Public Bridleway No.57 Wendover Wendover Between SP87231-06788 and SP86809-07357

Closure is required for safety reasons due to proximity of works to Bridleway

2 January 2020 30 September 2020
Public Footpath No.12 Great Missenden Great Missenden Between SP89493-01760 and SP90285- 02547

Closure is required for safety reasons to allow works on tower and wiring works

2 September 2019 30 September 2020
Public Footpath No.13 Great Missenden Great Missenden Between SP89656-01600 and SP90518-02416

Closure is required for safety reasons to allow works between towers, the installation of a new tower and restringing and removal of conductors between old and new towers.

2 September 2019 30 September 2020

Public Footpath No.5 Twyford

Twyford

Between SP68041-25763 and SP68104-25763

Site clearance works on existing farmland, which includes removing hedgerows and trees for HS2/ fusion.

4 March 2019

20 December 2019

Public Footpath No.6 Steeple Claydon

Steeple Claydon

Between SP69010-26334 and SP68104-25763

Site clearance works on existing farmland, which includes removing hedgerows and trees for HS2/ fusion.

4 March 2019 20 December 2019

Public Footpath No.12 Steeple Claydon

Steeple Claydon

SP69086-24798

Site clearance works on existing farmland, which includes removing hedgerows and trees for HS2/ fusion.

4 March 2019 20 December 2019
Public Footpath No.30 Grendon Underwood

Grendon Underwood

SP470266-222769 and SP470573-223072

HS2 Works

14 October 2019 30 April 2020
Public Footpath No.13a Wendover

Wendover

From SP86649-07551 to SP86622-07263

Archaeological recording across the worksite

20 November 2019 1 May 2020

 